Home > Urban Regeneration > Major Projects > Improvement of the Residential Environment Around Sipjeong 2

Improvement of the Residential Environment Around Sipjeong 2

Project Overview

Project Overview
Location 216, Sipjeong-dong, Bupyeong-gu, Incheon
Area 192,401.70 ㎡
Number of Housing Units A total of 5,678 housing units (1,550 housing units purchased by property owners including landowners, 550 public rental housing units (300 permanent rental housing units and 250 public rental housing units), and 3,578 publically supported private rental housing units)

Project Timeline

  • February 5, 2007 Established a renewal plan and announced the area selected for the project
  • November 8, 2009 Announced approval for the project implementation
  • November 11, 2015 Signed an MoU regarding the publically supported private rental housing project
  • December 28, 2015 Changed the project implementer (from LH to IMCD)
  • January 6, 2016 Established the renewal plan (revised) and requested the approval for the change of the area selected for the project
  • January 15, 2016 Made an announcement for residents
  • February 24, 2016 Passed the urban planning committee’s evaluation
  • March 7, 2016 Announced the change of the area selected for the project (by Mayor of Incheon Metropolitan City)
  • April 18, 2016 / April 22, 2016 Underwent the construction and traffic impact assessments
  • April 2016 Conducted survey on lands and obstructing properties
  • June 10, 2016Requested the approval for the revision of the project implementation plan
  • June 21 – July 5, 2016 Made an announcement for residents
  • June–July 2016 Negotiated with relevant agencies
  • July 22, 2016 Announced approval for the project implementation
  • January 22, 2017 Hosted an assembly for the management and disposal of the former properties
  • March 8, 2017 Announced approval for the former property management and disposal plan
  • March 10, 2017 Announced compensation and information disclosure
  • April 19–30, 2017 Accepted applications for relocation assistance along with relocation plans
  • July 19, 2017 Assessed the business proposals submitted by rental business operators
  • July 20, 2017 Selected preferred bidders among rental business operators
  • July 21, 2017 Announced approval for the project implementation
  • November 24, 2017 Announced approval for the former property management and disposal plan (revised)
  • July 2018 Initiated the demolition
  • November 2018Initiated the construction
  • 2022 Complete the construction
  • 2022 Let new residents move in
  • 2022 Distribute cash liquidation

The abovementioned timeline may be subject to change under certain circumstances including any changes to the project plan.

Project Procedure

Project Procedure

Project Procedure

Project Procedure

42, Inju-daero 914beon-gil, Namdong-gu, Incheon (21591), KOREA

Tel +82-32-260-5000  |  E-mail webmaster@idtc.co.kr

Copyright @ Incheon Metropolitan City Development Corporation. All Right Reserved.